Initial ARRA Project Plan 

3/31/2009 
3. County 4. Congressional District 5. Federal-Aid Project Number 6. State Project Number or Identification Number 7. Project Type 8. Project Name 9. Project Description 10. Project Purpose 11. Total cost Estimate (in 000s) 12. Scheduled Completion month (mm/yyyy) 13. Project Rationale 14. EDA (Y/N) 15. NEPA Class Action 16. NEPA Milestone Completed 17. NEPA Milestone Date (mm/dd/yyyy) 18. Types of Federal Permits 19. Number of Federal Permits 20. Status of Federal Permits 21. Rt # 22. Begin Mile 23. End Mile 24. Length (Miles)
051 01 ERP-0250(183)D S326-250-37.88 I Bellaire I/C Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $504 10/2009 1,4 Y CE-d CE 3/9/2009 NA 0 NA US250 37.88 37.88 NA
061 01 ERP-0793(222)D S331-79-152.53 I Westover Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $951 10/2009 1,4 N CE-d CE 3/9/2009 NA 0 NA I-77 152.53 153.01 0.48
107 01 ERP-0773(399)D S354-77-158.68 I Buck Run Road Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $350 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 165.15 158.69 6.46
107 01 ERP-0773(399)D S354-77-158.68 I Wolf Run Road Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $314 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 162.71 158.69 4.02
107 01 ERP-0773(399)D S354-77-158.68 I County Rt 25 Overpass  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $360 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 158.69 158.69 NA
107 01 ERP-0773(402)D S354-77-176.41 I I-77/US50 I/C  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $329 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 176.41 176.42 0.01
107 01 ERP-0773(402)D S354-77-176.41 I Worthington Creek Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $447 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 177.94 176.42 1.52
107 01 ERP-0773(402)D
S354-77-176.41
I WV 31 Overpass BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $272 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 183.31 176.42 6.89
107 01 ERP-0773(402)D S354-77-176.41
I Williamstown I/C BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $287 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-77 185.87 176.42 9.45
077 01 ERP-0068(135)D S339-68-18.03 I Laurel Run Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $793 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-68 18.03 18.03 NA
041 02 ERP-0792(156)D S321-79-98.40 I Stonecoal Creek Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $603 11/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-79 101.34 98.51 -2.83
041 02 ERP-0792(156)D S321-79-98.40 I County Rt 14 Overpass BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $610 11/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-79 98.40 98.51 0.11
007 02 ERP-0792(158)D S304-79-79.12 I Little Kanawha River Br BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $1,411 10/2009 1,4 Y CE-d NA NA NA 0 NA I-79 79.12 79.12 NA
007 02 ERP-0792(158)D S304-79-79.12 I Oil Creek Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $759 10/2009 1,4 Y CE-d NA NA NA 0 NA I-79 79.56 79.12 0.44
087 02 ERP-0792(160)D S344-79-33.99 I Wallback I/C BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $777 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-79 33.99 34.05 0.06
071 02 ERP-0033(320)D S336-33-19.21 I Judy Gap Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $462 10/2009 1,4 Y CE-d CE 3/2/2009 NA 0 NA US33 19.21 19.26 0.05
063 03 ERP-0003(216)D S332-3-0.01 I Alderson Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $695 10/2009 1,4 Y CE-d CE 3/2/2009 NA 0 NA WV3 0.01 0.18 0.17
055 03 ERP-0460(038)D S328-460-21.70 I Oakvale Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $974 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA US460 21.70 21.80 0.10
059 03 ERP-0119(338)D
S330-119-11.73 I West Belo Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $462 10/2009 1,4 Y CE-d CE 3/25/2009 NA 0 NA US119 11.73 11.78 0.05
011 03 ERP-0641(332)D S306-64-13.33 I Cedar Crest Bridge BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $310 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-64 13.33 13.33 NA
011 03 ERP-0641(332)D S306-64-13.33 I County Rt 26 Overpass BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $276 10/2009 1,4 Y CE-d CE 1/14/2009 NA 0 NA I-64 13.33 18.47 5.14
019 03 ERP-0019(337)D S310-19-15.37 I New River Gorge Bridge  BRIDGE LMC 14: Bridge Rehabilitation - No Added Capacity $1,028 10/2009 1,4 Y CE-d NA NA NA 0 NA US19 158.69 158.69 NA
007 02 ERP-0792(161)D S304-79-51.46 I Kenton Meadows N &S BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $1,969 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA I-79 51.47 51.75 0.28
087 02 ERP-0792(162)D S344-79-25.79 I Amma/Big Sandy Bridge N&S  BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $1,621 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA I-79 25.79 25.97 0.18
071 02 ERP-0009(194)D S336-9-9.24 I 4-U Bridge BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $232 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA Co9 9.24 9.24 0.00
007 02 ERP-0792(167)D
S304-79-78.18 I Saltlick Creek NB & SB  BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $793 10/2009 1,4 Y CE-d CE 2/23/2009 NA 0 NA I-79 78.18 78.30 0.12
043 03 ERP-0119(339)D S322-119-7.99 I Little Coal River  BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $1,603 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA US119 7.99 8.03 0.04
025 03 ERP-0644(170)D S313-64-179.35 I Mountain Ave Bridge N & S  BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $1,188 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA I-64 179.36 179.54 0.18
011 03 ERP-0052(271)D S306-52-0.74 I Madison Avenue O/P Bridge  BRIDGE C&P  14: Bridge Rehabilitation - No Added Capacity $259 10/2009 1,4 Y CE-d CE 2/5/2009 NA 0 NA US52 0.73 0.74 0.01
103 01 ERP-0017(086)D S352-17-3.68 I McBee BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $700 05/2010 1,4 Y CE-d CE 2/13/2009 NA 0 NA Co17 3.68 3.69 0.01
091 01 ERP-0007(219)D S346-7-3.21 I Irontown Girder BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $750 10/2009 1,4 Y CE-d NA NA NA 0 NA Co7 3.20 3.20 NA
051 01 ERP-0074(051)D S326-74-16.80 I Shepherd Bridge BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $2,000 10/2009 1,4 Y CE-d CE 8/18/2008 404 1 Completed Co74 16.80 16.85 0.05
091 01 ERP-0003(221)D S346-3-0.16 I Berry Run BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $550 05/2010 1,4 Y CE-d NA NA NA 0 NA Co3 0.16 0.16 NA
095 01 ERP-0013(056)D S348-13-6.06 I Walnut Fork BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $800 05/2010 1,4 Y CE-d NA NA NA 0 NA Co13 6.06 6.07 0.01
083 02 ERP-0219(299)D S342-219-28.50 I Jones Run BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $900 10/2009 1,4 Y CE-d CE 2/26/2009 404 1 Completed US219 28.50 28.51 0.01
041 02 ERP-1191(007)D S321-119/1-0.10 I Sleeths Run BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $1,200 10/2009 1,4 Y CE-d CE 2/5/2009 404 1 Completed Co119/01 0.09 0.11 0.02
039 02 ERP-0015(078)D S320-15-13.71 I Middle Fork  BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $500 05/2010 1,4 N CE-d CE 1/20/2009 NA 0 NA Co15 13.71 13.72 0.01
039 02 ERP-0271(001)D S320-27/1-1.10 I Edens Fork BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $750 05/2010 1,4 N CE-d CE 3/13/2009 NA 0 NA Co27/01 1.10 1.13 0.03
053 02 ERP-0029(022)D S327-29-5.59 I Arlee Slab BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $500 05/2010 1,4 Y CE-d CE 2/18/2009 NA 0 NA Co29 5.59 5.60 0.01
083 02 ERP-0062(832)D S342-62-0.08 I Lower Mingo BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $1,000 05/2010 1,4 Y CE-d NA NA NA 0 NA Co62 0.08 0.09 0.01
071 02 ERP-0012(048)D S336-12-4.15 I Deer Run Park BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $575 10/2009 1,4 Y CE-d CE 2/10/2009 NA 0 NA Co12 4.15 4.15 NA
071 02 ERP-0033(327)D S336-3/3-0.73 I Rough Run BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $875 05/2010 1,4 Y CE-d NA NA NA 0 NA Co3/3 0.73 0.74 0.01
099 03 ERP-0411(002)D S350-41/1-0.01 I Turkey Creek Pony Truss BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $1,600 10/2009 1,4 Y CE-d CE 1/28/2009 401,404 2 Applied/Pending Co41/1 0.01 0.01 NA
019 03 ERP-1601(001)D S310-160/17-0.01 I Michigan Ave BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $625 10/2009 1,4 Y CE-d CE 3/9/2009 NA 0 NA Co160/17 0.01 0.01 NA
067 03 ERP-1919(002)D S334-19/19-0.03 I Peters Creek BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $650 10/2009 1,4 Y CE-d CE 2/20/2009 NA 0 NA Co19/19 0.03 0.03 NA
063 03 ERP-0238(046)D S332-23/8-1.93 I Indian Creek BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $775 10/2009 1,4 Y CE-d NA NA NA 0 NA Co23/8 1.93 1.93 NA
025 03 ERP-0099(099)D S313-9/9-0.14 I Sinking Creek BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $550 10/2009 1,4 Y CE-d NA NA NA 0 NA Co9/9 0.14 0.14 NA
047 03 ERP-1659(001)D S324-16/59-0.01 I South Roselawn St BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $575 10/2009 1,4 Y CE-d NA NA NA 0 NA Co16/59 0.01 0.01 NA
055 03 ERP-0385(001)D S328-38/5-0.85 I Jug Neck BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $550 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA Co38/5 0.85 0.86 0.01
025 03 ERP-0206(001)D S313-20/6-1.00 I Greenbrier Ave BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $625 10/2009 1,4 Y CE-d CE 3/12/2009 NA 0 NA Co20/6 0.98 1.02 0.04
081 03 ERP-0034(067)D S341-3/4-2.12 I Horse Creek  #5 BRIDGE REPLACE 11: Bridge Replacement - No Added Capacity $575 10/2009 1,4 Y CE-d NA NA NA 0 NA Co3/4 2.12 2.13 0.01
095 01 ERP-0018(119)D S348-18-11.12 I WV 18,  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $1,228 10/2009 1,4 Y CE-d NA NA NA 0 NA wv18 11.12 11.62 0.50
071 02 ERP-0220(182)D S336-220-13.30 I Smith Creek to Franklin Rd  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $1,000 10/2009 1,4 Y CE-d CE 1/28/2002 NA 0 NA US220 13.30 13.48 0.18
099 03 ERP-0037(028)D S350-37-18.64 I Bethesda Road  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $209 10/2009 1,4 Y CE-d CE 2/10/2009 NA 0 NA WV37 18.64 18.67 0.03
019 03 ERP-0060(252)D S310-60-14.60 I Chimney Corner  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $210 10/2009 1,4 Y CE-d NA NA NA 0 NA US60 14.60 14.61 0.01
081 03 ERP-0003(222)D S341-3-29.13 I Metalton Road  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $376 10/2009 1,4 Y CE-d CE 2/24/2009 NA 0 NA WV3 29.13 29.14 0.01
067 03 ERP-0020(254)D S334-20-26.75 I Curtin  SLIDES 4R: Maintenance, Restoration, and Rehanbilitation $165 10/2009 1,4 Y CE-d NA NA NA 0 NA WV20 26.75 26.76 0.01
085 01 ERP-0050(276)D S343-50-26.98 I Nutter Farm-Camp Run Rd.  RESURFACING  5:4R: Maintenance Restoration $1,492 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA US50 26.98 29.16 2.18
085 01 ERP-0050(277)D S343-50-31.65 I Camp Run-Ellenboro Rd. RESURFACING  5:4R: Maintenance Restoration $1,494 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA US50 31.65 33.88 2.23
097 02 ERP-0033(321)D S349-33-10.87 I Buckhannon-Elkins  RESURFACING  5:4R: Maintenance Restoration $1,759 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA US33 10.87 15.40 4.53
067 03 ERP-0019(338)D S334-19-15.70 I Fockler Branch-Muddlety  RESURFACING  5:4R: Maintenance Restoration $2,099 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA US19 15.70 17.64 1.94
055 03 ERP-0460(039)D S328-460-4.29 I Bluefield Road  RESURFACING  5:4R: Maintenance Restoration $2,059 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA US460 4.29 5.96 1.67
069 01 ERP-0070(158)D S335-70-0.00 I Wheeling-Valley Grove Rd Approach Slabs  RESURFACING  5:4R: Maintenance Restoration $3,592 10/2009 1,4 N CE-d CE 1/22/2009 NA 0 NA I70 X 0.50 NA
049 01 ERP-0793(223)D S325-79-136.68 I Fairmont-Pricketts Fort  RESURFACING  5:4R: Maintenance Restoration $1,538 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA I-79 136.68 138.87 2.19
061 01 ERP-0068(137)D S331-68-7.20 I Pierpont-Cheat Lake RESURFACING  5:4R: Maintenance Restoration $1,321 10/2009 1,4 N CE-d CE 2/9/2009 NA 0 NA I-68 7.20 9.40 2.20
087 02 ERP-0792(168)D S344-79-29.48 I Amma - Wallback Rd RESURFACING  5:4R: Maintenance Restoration $2,943 10/2009 1,4 Y CE-d CE 2/25/2009 NA 0 NA I-79 29.48 33.97 4.49
003 02 ERP-0811(104)D S302-81-21.35 I Falling Waters-Maryland  RESURFACING  5:4R: Maintenance Restoration $2,516 10/2009 1,4 Y CE-d CE 2/9/2009 NA 0 NA I-81 21.35 26.00 4.65
007 02 ERP-0792(164)D S304-79-57.82 I Coon Knob-Gassaway Rd  RESURFACING  5:4R: Maintenance Restoration $3,229 10/2009 1,4 Y CE-d CE 3/2/2009 NA 0 NA I-79 57.82 64.81 6.99
003 02 ERP-0811(105)D S302-81-0.00 I Virginia State Line-Inwood  RESURFACING  5:4R: Maintenance Restoration $2,371 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA I-81 X 4.27 NA
025 03 ERP-0644(171)D S313-64-174.61 I Harts Run  RESURFACING  5:4R: Maintenance Restoration $2,917 10/2009 1,4 Y CE-d CE 3/2/2009 NA 0 NA I-64 174.61 176.11 1.50
025 03 ERP-0644(172)D S313-64-160.00 I Alta  RESURFACING  5:4R: Maintenance Restoration $1,705 10/2009 1,4 Y CE-d CE 1/22/2009 NA 0 NA I-64 160.00 161.00 1.00
011 03 ERP-0641(334)D S306-64-27.88 I Milton to CR 60/19  RESURFACING  5:4R: Maintenance Restoration $1,191 10/2009 1,4 N CE-d CE 1/22/2009 NA 0 NA I-64 27.88 29.44 1.56
061 01 ERP-0705(011)D S331-705-2.55 I Orchard By-Pass  RESURFACING  5:4R: Maintenance Restoration $850 10/2009 1,4 N CE-d CE 2/3/2009 NA 0 NA WV705 2.55 3.55 1.00
073 01 ERP-0002(474)D S337-2-0.00 I Waverly-Willow Island Road  RESURFACING  5:4R: Maintenance Restoration $999 10/2009 1,4 Y CE-d CE 3/3/2009 NA 0 NA WV2 X 2.72 NA
057 01 ERP-0220(183)D S329-220-13.96 I Mineral St,  RESURFACING  5:4R: Maintenance Restoration $1,131 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US220 13.96 14.83 0.87
051/069 01 ERP-0250(184)D S326-250-34.70 I McMehen-Wheeling  RESURFACING  5:4R: Maintenance Restoration $5,696 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US250 34.70 40.14 5.44
085 01 ERP-0016(205)D S343-16-14.13 I Washburn-Harrisville RESURFACING  5:4R: Maintenance Restoration $1,159 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV16 14.14 17.40 3.26
093 01 ERP-0219(302)D S347-219-10.09 I Parsons-Mackeyville  RESURFACING  5:4R: Maintenance Restoration $940 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US219 10.09 11.29 1.20
041 02 ERP-0019(339)D S321-19-22.08 I Ben Dale-Weston Rd RESURFACING  5:4R: Maintenance Restoration $351 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US19 22.08 23.97 1.89
035 02 ERP-0033(322)D S318-33-14.00 I Ripley-Frozencamp  RESURFACING  5:4R: Maintenance Restoration $1,303 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US33 14.00 18.16 4.16
083 02 ERP-0219(303)D S342-219-40.60 I Elkins-Highland Park  RESURFACING  5:4R: Maintenance Restoration $1,646 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US219 40.60 41.80 1.20
097 02 ERP-0020(255)D S349-20-16.05
I French Creek-Adrain Rd
RESURFACING  5:4R: Maintenance Restoration $370 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV20 16.05 18.07 2.02
013 02 ERP-0016(206)D S307-16-28.04 I Grantsville-Smithville  RESURFACING  5:4R: Maintenance Restoration $639 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV16 28.04 29.35 1.31
039 02 ERP-0094(168)D S320-94-1.47 I Hernshaw-Marmet RESURFACING  5:4R: Maintenance Restoration $2,381 10/2009 1,4 N CE-d CE 2/3/2009 NA 0 NA WV94 1.48 7.00 5.52
027 02 ERP-0050(278)D S314-50-8.50 I Romney Street  RESURFACING  5:4R: Maintenance Restoration $4,000 10/2009 1,4 Y CE-d NA NA 404,NPDES 2 Completed US50 8.50 10.08 1.58
047 03 ERP-0080(032)D S324-80-3.40 I Beartown-Iaeger Rd  RESURFACING  5:4R: Maintenance Restoration $961 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV80 3.40 5.40 2.00
019 03 ERP-0061(065)D S310-61-17.17 I Kincaid-Page  RESURFACING  5:4R: Maintenance Restoration $441 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV61 17.17 18.41 1.24
099 03 ERP-0052(263)D S350-52-52.02 I Stonecoal Road-Mingo Co. Line  RESURFACING  5:4R: Maintenance Restoration $1,494 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US52 52.03 54.32 2.29
055 03 ERP-0052(264)D S328-52-5.17 I Pinnacle Rock-Lorton Lick  RESURFACING  5:4R: Maintenance Restoration $1,338 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US52 5.17 6.67 1.50
099 03 ERP-0052(265)D S350-52-6.51 I WV 75-Whites Creek Road  RESURFACING  5:4R: Maintenance Restoration $993 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA US52 5.51 11.93 6.42
081 03 ERP-0016(207)D S341-16-17.06 I S Oakwood Ave - Bus Station  RESURFACING  5:4R: Maintenance Restoration $635 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV16 17.06 17.53 0.47
005 03 ERP-0003(217)D S303-3-20.33 I Peytona-Racine  RESURFACING  5:4R: Maintenance Restoration $673 10/2009 1,4 Y CE-d CE 2/3/2009 NA 0 NA WV3 20.32 21.99 1.67
063 03 ERP-0219(300)D S332-219-0.50 I North Peterstown  RESURFACING  5:4R: Maintenance Restoration $925 10/2009 1,4 Y CE-d CE 2/3/2009 NOI 1 Completed US219 0.50 2.84 2.34
067 03 ERP-0039(406)D S334-39-35.12 I Deer CreekÂ